The project
Racking installed inside a working building
The storage area sits inside an existing warehouse, so the crew worked under a roof that was already in place, with cable trays, sprinkler lines and lighting overhead. Each bay was set out and levelled against the building, and the layout had to clear the services above.
Installation went in phases so the client could keep receiving stock, and the site was handed over with the levels and tightening checked and documented.
How we built it
From the first upright to handover
Uprights and bracing
Uprights raised, plumbed and braced bay by bay.

Beams and pallet levels
Levels set in sequence, with the locking pins checked on every beam.

Decking
Steel decking fitted to the levels that carry it.

Checks and handover
Levels, tightening and damage inspected, then handed over with the documents the site required.

Gallery