The project
Several picking levels, one steel structure
Our crew installed a multi-level pick module for SEUR in Portugal: a steel structure with walkway floors on several levels and carton flow racking, where orders are picked by hand and cartons roll to the pick face.
We worked for Icon, the system provider, for eleven months in 2025, with a crew of 25 installers.
How we built it
From the slab to the top level
01
Columns and anchoring
Columns set out, plumbed and anchored to the slab.

02
Floors and walkways
Beams and floor panels fitted to build each walkway level.

03
Carton flow racking
Flow lanes installed at the right slope so cartons roll to the pick face.

04
Checks and handover
Levels, fixings and flow lanes checked before handover to the provider.